|
2025, Vol. 37,No. 3 Published:25 September 2025 |
Previous
|
|
|
Calculation of Stagnation
Pressure of Centrifugal Compressor Systems
Wang Zhenwei
2025, 37 (3):
1-5.
The stagnation pressure of
a centrifugal compressor system impacts the design of the compressor body?, ?auxiliary
systems? (e.g., seals) and ?related process systems? (e.g., suction drums). Rigorous
and accurate calculation formulas are derived based on thermodynamic theory.
Several simplified formulas are developed. The errors of several calculation
methods are compared and analyzed through calculations, and a simplest calculation
method is recommended for the stagnation pressure of three key compressors in
ethylene plants.
References |
Related Articles |
Metrics
|
|
Discussion on Ways to Reduce Exhaust Pressure in
Driving Turbine for Propylene Refrigeration Compressor
Dong Yalong, Dai Chuan, Zhang Zhifei, Ma Jianchao, Liu Guangyi
2025, 37 (3):
6-8.
This paper introduces
the high exhaust pressure in the driving turbine for propylene refrigeration
compressor in the 220 kt/a ethylene plant of a petrochemical company. Through
technical research, design optimization and the implementation of technical
measures, the working efficiency of the turbine is further improved while
eliminating the bottleneck of high exhaust pressure, thus achieving the goal of
energy saving and consumption reduction and eliminating the operational hazards
in the plant. The operational efficiency of the plant is improved and the cost
is reduced through minor modifications in local areas.
References |
Related Articles |
Metrics
|
|
Application and
Practice of Dry Gas Seal Systems in Compressors of Ethylene Plants
Zhang Jiangping, Yang Xing, Shen Guofeng, Shen Shundi
2025, 37 (3):
9-13.
In a 1,190 kt/a ethylene plant, seven centrifugal
compressors utilizes dry gas seal system. During operation, the failure or
damage of the dry gas seal system resulted in the interlock shutdown of
cracking gas compressor. This paper briefly explains the principle and control
of dry gas seal system, and summarizes the on-site practical experience and
application suggestions through typical cases of dry gas seal application over
the years.
References |
Related Articles |
Metrics
|
|
Impact of Heavier Cracking Feedstocks on Heavy
Component Separation Towers and the Countermeasures
Huang Yixiang, Zheng Wenjing, Li Heng
2025, 37 (3):
14-18.
With
heavier and deteriorated cracking feedstocks, an 800 kt/a steam cracking unit faces
two major challenges, i.e., the high-load operation control of heavy component separation towers and the increased
fouling rates due to the heavier feedstock. This paper analyzes the impact of
long-term high-load operation of heavy component separation towers and the
material polymerization and fouling on the normal operation of the process system.
Some optimization measures are proposed from the aspects of process operation optimization,
equipment maintenance strategies and design debottlenecking modifications to
ensure the long-term safe production of the heavy component separation towers
in steam cracking unit.
References |
Related Articles |
Metrics
|
|
Research and Application of Process
Optimization for Natural Gas to Methanol Plants
Xue Xinchao, Zhang Lei, Fu Yinhua, Li Bing, Tang Zhibin
2025, 37 (3):
19-24.
The pre-processes of the hydrogen production unit and the methanol unit
of a certain company are highly consistent, and the process parameters are
similar. Due to the shutdown of reformer in the hydrogen production unit, in
order to meet the hydrogen demand for startup after maintenance,
high-temperature conversion gas produced by the methanol unit was used as the feed
gas for medium-temperature shift reaction in the
hydrogen production unit. Through process optimization and the co-production
and co-adjustment strategy, the conversion process of methanol unit was closely
connected with the process flow of hydrogen production unit including medium-temperature
shift, compressor, medium-temperature shift system and feedstock preheating
furnace, so as to meet the hydrogen demand for start-up of production units. At
the same time, the start-up time of the hydrogen production unit could be
reduced from 5 days to 36 hours, greatly improving the emergency hydrogen
production capacity of the unit. When the ethylene unit was in operation and
the total amount of crude hydrogen and wet hydrogen was 580 kg/h, the optimized
process of the new methanol unit and hydrogen production unit could meet the
maximum external hydrogen supply of 12,506 m3/h. Through process
optimization and co-production and co-adjustment, the operation bottleneck of the
hydrogen production unit was eliminated. At the same time, the mutual backup of
hydrogen production unit was achieved, the task of guaranteeing hydrogen supply
during startup was completed, and the dual goals of technical research and
quality improvement with efficiency enhancement were achieved.
Related Articles |
Metrics
|
|
Application of BTX Aromatics Extraction Technology in Ethylene Crackers
Lyu Hongtao, Liang Duo, Wang Jianhui, Chen Ming
2025, 37 (3):
25-29.
Pyrolysis gasoline
from ethylene cracker undergoes pre-fractionation to remove C5 and
lighter components and C9+ components, and then undergoes
two-stage hydrogenation to hydrogenate olefins into saturated hydrocarbons and
remove impurities such as sulfur, nitrogen and oxygen to obtain hydrogenated
pyrolysis gasoline. The hydrogenated pyrolysis gasoline is separated by BTX
extraction and distillation to obtain products such as benzene, toluene and
mixed xylene. In this paper, the technological route and operation key points
of BTX aromatics extraction unit with hydrogenated pyrolysis gasoline as the
feed are analyzed. It differs from the traditional aromatics extraction in the
introduction of raffinate extraction system and water washing coupling process,
which recovers benzene from non-aromatic hydrocarbons and removes solvents from
non-aromatic hydrocarbons. The technical problem of separating C8 non-aromatics from aromatics in BTX extraction can be solved, and the solvent
quality deterioration caused by the accumulation of heavy components can be
solved by the coupling process. The two separation columns of toluene, mixed
xylene and heavy aromatics in the aromatics distillation system are integrated
into a single column to obtain on-spec toluene and mixed xylene products.
References |
Related Articles |
Metrics
|
|
Optimization of Shutdown Process for Quench Systems of Ethylene Plants
Yuan Bo
2025, 37 (3):
30-34.
This article focuses on the main operations during the shutdown of
quench system of ethylene plant, and analyzes and studies the difficulties in
emptying quench oil, the high oil content of quench water, and the easy
blockage of discharge valve during the emptying operation. To solve the problem
in emptying the quench oil, an optimization method is proposed for the emptying
operation of quench system. By utilizing the height difference between the
pipeline, tower tank and heat exchanger users of the quench oil system and the
inlet pipeline of quench oil delivery pump and heavy fuel oil pump, temporary
pipelines are configured to increase the number of available quench oil
delivery pumps, improve the delivery flow rate, reduce the workload of
operators, and effectively shorten the emptying time of the system and increase
the recovery of quench oil. To solve the problem of high oil content of quench
water, a method of preliminary separation and recovery of gasoline through
cooling and settling is proposed. To solve the problem of easy blockage of
discharge valve in the quench system, a backwashing method is proposed.
Related Articles |
Metrics
|
|
Cause Analysis and
Countermeasures for Short Operating Cycle of Reboilers in Butadiene
Distillation Towers
Zhang Yan, Wang Jianfeng, Huang Chaobo, Heng Xinjiang, Qin Chaofeng
2025, 37 (3):
35-37.
Polymer blockage in reboilers of butadiene distillation towers can
significantly reduce the heat transfer efficiency of reboilers, leading to
increased energy consumption and insufficient product purity (such as
1,3-butadiene purity < 99.2%), and posing a threat to the long-term
operation of the unit. Design defects cause the liquid phase lines of the reboilers
in acetylene distillation tower and butadiene distillation tower to be at the
lowest point of the entire tower, resulting in the accumulation of polymers and
TBC inhibitors, which exacerbates the pipeline blockage and decreases the heat
transfer efficiency. No rupture disc is installed upstream the safety valve,
and the polymerization of high-concentration butadiene may block or swell the
safety valve, posing a safety hazard. Insufficient bypass opening (below 2 turns)
of the pressure regulating valve PV24006 results in poor medium fluidity and easy
polymer formation in dead legs. In addition, TBC inhibitors need to be
accurately added at the designated injection points (the overhead gas phase
line and reflux line of acetylene/butadiene towers). Insufficient injection can
cause polymerization at the bottom and shorten the operating cycle of reboilers.
Excessive injection can lead to equipment blockage and increased costs.
Uncontrolled oxygen content and tower pressure can directly trigger
polymerization reactions, block the equipment, and force the system to shut
down for cleaning.
Related Articles |
Metrics
|
|
Analysis of Power
Supply Failure of Ethylene Feed Valve in Polyethylene Plants
Kong Lingjiang
2025, 37 (3):
38-39.
The abnormal closure
of the ethylene feed valve in polyethylene plant caused disturbances in
polymerization unit, and emergency measures were taken to avoid the shutdown of
the plant. This article uses root cause analysis to investigate the factors
causing abnormal valve operation, and ultimately determines that the
insufficient power supply of the control system failing to meet the needs of
on-site equipment is the cause. The accident potential is eliminated by taking
corrective measures, and considerations for the power supply design of control
system are proposed.
Related Articles |
Metrics
|
|
Cause Analysis of Leakage in Pressure Gauge Impulse
Line of Radiant Coil in a Cracking Furnace
Yang Jicheng, Li Huitao, Pan Yanjun, Zhou Jiacheng, Sun Yaowei
2025, 37 (3):
40-42.
A comprehensive investigation was conducted on the
leakage at the root weld of impulse line of the radiant coil in cracking
furnace of a 1.2 Mt/a ethylene plant. Through macroscopic morphology, material testing,
metallographic examination, electron microscopy scanning and energy spectrum
analysis, it was found that the cracking at this location was due to the
decrease in the toughness of small tube structure, resulting in fatigue cracks
under structural stress. The reason was that severe stress concentration occurred
at the connection between the main pipe and the branch pipe. Material
sensitization occurred during long-term service at high temperature, leading to
microcracks at the weld seam. These cracks gradually expanded from the outside
to the inside, ultimately forming through-thickness cracks and causing leakage.
References |
Related Articles |
Metrics
|
|
Piping Design of Ethylene Cracking Gas Main Valve
Assembly
Liu Ting
2025, 37 (3):
43-47.
Ethylene cracking gas main valve assembly is one of
the key equipment in ethylene cracking furnace. This paper, based on the
engineering example of a newly constructed ethylene plant, discusses the role
and importance of the stable operation of cracking gas main valve for the
entire process of cracking furnace, elaborates on the optimization of purge
steam line for the main valve, and discusses the layout of outlet pipeline of
the main valve as well as two design schemes for the support configuration of
the main valve.
References |
Related Articles |
Metrics
|
|
Periodic
Inspection of Ethylene Spherical Tanks in Ethylene Plants
Duan Zhongxin, Zhao Fei, Zhao Pan, Liang Duo, Li Zhiyuan
2025, 37 (3):
48-51.
The
tank farm for the 600 kt/a ethylene plant of PetroChina Tarim Petrochemical Company
is equipped with eight ethylene spherical tanks with a volume of 3,053 m3. In
2023, the first periodic inspection was carried out for the ethylene spherical
tanks after they were put into operation. While strictly implementing the Pressure Vessels Periodical Inspection Regulation, the main damage
mechanism and failure mode of the spherical tanks were fully considered. The
inspections mainly include document review, macroscopic examination, wall
thickness measurement, surface defect detection, ultrasonic testing, hardness
testing, and safety accessory inspection. During the process disposal,
scaffolding erection, weld grinding and other tasks prior to the inspection,
safety technical disclosure was strictly conducted with the construction
company, and construction and management were carried out according to the
standardized templates, so as to ensure the safe and efficient completion of
the inspection.
References |
Related Articles |
Metrics
|
|
Cause
Analysis and Countermeasures for Buckling Deformation of Inner Tube in Jacket
of Cold Dry Flare in Ethylene Plant
Yu Dejiang, Li Lei, Zhang Lei, Ha Da, Zhang Hu
2025, 37 (3):
52-57.
During the process operation and accident discharge of an ethylene
plant, it was found that the back pressure of flare was abnormally increased
during equipment emptying and purging as well as acetylene hydrogenation
reactor switching and discharging to cold dry flare. During the major overhaul
in 2024, endoscopes and tube robots were used to check the inner tube in jacket
of the cold dry flare, and the inner tube was found to be severely deformed.
The causes of inner tube deformation were analyzed by calculating the
parameters of the cold dry flare including daily operation, harsh working
conditions and piping design, and targeted solutions were developed to ensure
the safe emission of the flare system.
Related Articles |
Metrics
|
|
Study
and Analysis of Anaerobic Unloading Process of the Second Stage Catalysts for
Pyrolysis Gasoline Hydrogenation
Xiao Wenkai, Jiang Hao, Xu Derong, Dong Wanjun, Liu Hengxu
2025, 37 (3):
58-60.
The
catalysts in the second stage reactor of the pyrolysis gasoline hydrogenation
unit of PetroChina Sichuan Petrochemical Co., Ltd. was unloaded anaerobically
for the first time. This paper introduces the anaerobic unloading technology,
unloading process and the precautions. Safety risks such as fire, explosion,
poisoning and suffocation during catalyst unloading can be effectively reduced
through process handling and energy isolation, reliable gas supply system,
strict control of the work environment, enhanced process monitoring,
strengthened personnel training and education, and proper disposal of spent
catalysts.
References |
Related Articles |
Metrics
|
|
Application of Mechanical Cleaning Technology in Cleaning of Sewage Tanks in Chemical Plants#br#
Zhang Youtian, Yang Zhengchao, Zhang Daojun, Song Zhiqi, Du Biao
2025, 37 (3):
61-64.
Cleaning of sewage tanks in chemical plants has always been a high-risk
operation in confined spaces. In the past, personnel entered the tanks for
cleaning. The site smelled seriously, and the organic hydrocarbon content often
exceeded the standard. Personnel suffocation, poisoning, and fire and explosion
accidents are prone to occur during the cleaning. The control of the cleaning
process has always been a difficulty point. In order to prevent accidents, an
advanced mechanical cleaning technology was introduced from the perspective of
personal safety, health and environmental protection. It was applied in the
cleaning of sewage tank for the first time, and good results were achieved.
References |
Related Articles |
Metrics
|
|
Study
on operation safety management and control of aging ethylene plant during
winter
Sheng Zaihang, Li Shaopeng
2025, 37 (3):
64-68.
In
response to the frequent chain accidents of leakage–freeze expansion–fire in
domestic ethylene plants with ultra-long service cycle (>30 years) during
winter, this paper takes a rupture-and-fire incident on the drain line of an
ethylene cracking unit as the example, and reconstructs the release sequence
using multi-source data from DCS, GDS, weather stations and surveillance
cameras. Using Phast software, a three-stage leakage model of water → liquid
hydrocarbon → cracked gas is established and coupled with video frames. It is
confirmed that, under conditions of -15 ℃ heat-tracing failure and CUI
wall-thinning to 2.06 mm, the DN50 blind-end pipe suffers a 45° shear rupture
when internal pressure exceeds the freeze-expansion limit. A four-dimensional closed-loop management
strategy of design–inspection–warning–emergency for winter operation of aged
units is proposed, providing quantitative bases for standard upgrades of
similar installations in the industry.
References |
Related Articles |
Metrics
|
|